Honomu House Construction II

-  South Wall Concrete Pour

- Stairwell and North Wall  Construction and Concrete Pour

Tips for viewing pictures:

If all icon images do not display, hit the refresh button on your browser or click to view the large image.

Click on pictures for a larger (XGA), higher resolution image. The image will open in new window. Resize it for maximum picture size. When you click on other small pictures, they will open in this new window. You can use the ALT-TAB key combination to switch between windows if you are using a Windows based operating system. If you have having trouble viewing the pictures, consider upgrading to a new browser such as Mozilla or Firefox. Both are available for Linux, Mac and Windows systems at www.mozilla.org.  To save picture to your hard disk, right click on small image and select "save link as" and select the location where you want to store. Alternatively, if you are looking at the large image in its own window you can select "File Save Page As" from the main menu or right click on the image and select "Save Image As". My favorite image viewer is Irfanview.

June 9 - North wall and stair pour complete, sealing starts


June 8 - Forms ready for the pour


June 3 - Form work nears completion

 

June 1 - Rebar installation - north wall form work underway


May 27 - South wall forms come off, work starts on stair-well forms


Concrete Pour - Tuesday Morning, May 18